News from Clemens Kraft
13.07.2026
Construction of Føsseberge power plant is well underway
Construction of Føsseberge power plant, which is owned by Clemens Kraft and Skagerak Kraft, got off to a good start after a somewhat difficult beginning involving various authorities before all approvals were in place.
The power plant is located in Vang municipality, Innlandet county, and will utilise the flow of the Storåni river downstream from Lake Vangsmjøsa.
The head is 23 metres, from elevation 452 to elevation 429. Expected production is between 16 and 17 GWh.
Read more about Construction of Føsseberge power plant is well underway
13.07.2026
The Kvammadalselvi Development Project Is in Full Swing
Construction of the Kvammadalselvi power plant in Aurland Municipality, Vestland County, is fully underway. The power plant is being built with a fantastic view on the edge above the waterfall that plunges down the mountainside right next to the entrance to the Lærdal Tunnel.
Read more about The Kvammadalselvi Development Project Is in Full Swing
15.06.2026
Industry gathering and 20 years with Clemens Kraft
Since its beginnings two decades ago, Clemens Kraft has developed into Norway’s second-largest company in the small-scale hydropower sector. The anniversary was celebrated with an industry gathering at the Norwegian Museum of Cultural History, in typical Norwegian summer weather – alternating sunshine and rain. And no one likes rainy weather more than hydropower people.
Read more about Industry gathering and 20 years with Clemens Kraft
13.04.2026
New collaboration on inflow calculations
Water – when and how much does it arrive, and when is it worthwhile to use it? Clemens Kraft will now collaborate with Expert Analytics to develop better inflow calculations.
Read more about New collaboration on inflow calculations
09.03.2026
Ministry rejects million-kroner fine against Kupekraft
Last year, NVE fined Kupekraft – owned by Clemens Kraft – for violating licensing rules, but the Ministry of Energy concluded that no law had been breached.
Read more about Ministry rejects million-kroner fine against Kupekraft
06.03.2026
NVE public meeting about the Garbergelva River in Selbu
The municipal council chamber in Selbu was packed when NVE held its public meeting about Clemens Kraft’s plans for a power plant on the Garbergelva River, and among the audience were both skeptics and those who were enthusiastic.
Read more about NVE public meeting about the Garbergelva River in Selbu
02.03.2026
Winter idyll at Tokagjelet, but things are happening underground
When the river freezes, it is time for inspections underground. At Tokagjelet in Kvam, the water pipes are inspected and the power station is upgraded.
Read more about Winter idyll at Tokagjelet, but things are happening underground
11.02.2026
Public Consultation and Information Meeting - Garbergelva Hydropower Plant
Clemens Kraft AS submitted a notification, dated 11 November 2025, to the Norwegian Water Resources and Energy Directorate (NVE) regarding the planned development of the Garbergelva hydropower plant in Selbu Municipality. This has now been circulated for public consultation by NVE.
Read more about Public Consultation and Information Meeting - Garbergelva Hydropower Plant