The Flow Continues at Kvernfossen
The power plant generated its first hour of electricity on the grid in June 2021. After a testing period, the power plant was inspected and officially commissioned on 25 October.
Published 10.01.2022
Project manager Viggo, Mads and Petter from CKD were present. Jan-Helge Solheim from Hywer was also present, as they will operate this facility for Clemens Kraft for a period.
Location: Hyllestad Municipality, Vestland County
Turbine type: Kaplan
Generator capacity: 2.15 MVA
Cos ϕ: 0.9
Installed capacity: 1.9 MW
Annual production: 9.14 GWh
Head: 26.5 m
Discharge capacity: 9 m3/s
Minimum flow: 600 l/s (summer and winter)